2019 Roadwork Projects

5/10/2019

Blome Road is now open.

 

The Village of Indian Hill has several road projects scheduled for this year which include stabilizing landslides, culvert replacements, culvert repairs and bridge replacements. Projects starting under construction this week and next week are:

Blome and Spooky Hollow Roads

The first culvert under Blome Rd. has been installed, however, it will remain closed until the entire project is completed. On March 25th, Spooky Hollow Road will be closed at Blome Road to remove and replace the second culvert. Spooky Hollow Rd. and Blome Rd. will re-open the week of May 19th, weather permitting. Detour signs will be posted.

Other upcoming road closures (Dates subject to change)

  • South Given Rd Culvert Replacement 3/25/19-3/29/19 
  • Shawnee Run Rd Bikepath Bridge Repair TBD
  • Hopewell Landslide 5/6/19 - 6/7/19
  • Loveland Madeira Landslide 6/3/19 - 7/5/19
  • Demar Landslide 7/1/19 - 7/31/19
  • Remington Rd. Culvert Replacement 8/1/19 - 9/20/19
  • Keller Bridge Replacement 8/1/19 - 11/15/19
  • Muchmore Rd Landslide 8/1/19 - 9/13/19
  • Shawnee Run Rd Landslide 10/1/19 - 12/13/19

More Information


For concerns or questions you can contact the Public Works Department.
Village of Indian Hill
Public Works
6525 Drake Road
Cincinnati, Ohio 45243
Tel: 513-831-3712
FAX: 513-831-3897